The 'my last contractor walked off the job' call: how to take over half-finished work
By Holden Marsh, Editorial Director7 min read

TL;DR: Never give a firm phone price on a takeover job. Visit the site, inspect the existing work, take dated photos, and write down exactly which work you own and which work you do not.
“It just needs finishing” is not a scope of work
The caller usually says the last contractor quit, stopped showing up, or got fired. Then comes the phrase you will hear again and again: “It just needs finishing.”
That phrase tells you almost nothing.
On the walkthrough, the drywall may already be up over the plumbing and wiring. Nobody may know whether that rough-in was inspected. The “just finishing” job can turn into opening walls so you can see what you are building on.
That is why you look before you price.
The caller is often upset. They want to tell you everything the last contractor did wrong. Listen, but steer the call toward facts. Do not trash-talk the previous contractor. You have heard one side. Sometimes a contractor leaves because they were not paid. Sometimes the scope kept changing.
Ask what happened. Ask how many contractors have already worked on the job. If you would be the third contractor, write that down. It is not an automatic no. It is something you should know before you drive out.
Ask these questions before you put the job on your schedule
Keep this list beside the phone:
- What was the original job, and how far did the work get?
- Is there a signed contract with the other contractor, and has it been ended in writing?
- How much have you paid so far, compared with how much work got done?
- Was a permit pulled, and in whose name? Have any inspections been done?
- Are there materials on site, and who paid for them?
- Is anything urgent right now, such as an open roof, no water, no working kitchen or bathroom, or a move-in date?
The old contract matters. If it has not been ended in writing, the customer should sort that out before you start. You are not their lawyer. If they are unsure where they stand, they should ask one.
Ask about the money without taking sides. The amount paid and the amount of work completed can tell you what kind of dispute you may be walking into.
An old permit can stop your work before it starts
If the last contractor pulled the permit, it is usually in that contractor’s name.
A new contractor’s process for taking over the permit is decided by the local building department. That process differs from place to place. Call the building department before you start work, not after.
The same call should cover inspections. Ask whether any have been done. If nobody knows whether the rough-in was inspected, treat that as an open question until you have checked.
Unpaid people from the old job can still matter
In many states, a contractor, subcontractor, or supplier who did not get paid can file a lien on the property. The rules differ by state.
Ask the customer whether anyone from the last job says they are still owed money. Ask plainly. Do not give legal advice. You are finding out what the customer knows before you agree to take over the work.
Price the work you will perform, not the percentage left behind
Do not price the job by saying, “They were 60 percent done, so this is 40 percent of a full price.”
You have to check the existing work before you can build on it. You may need to fix or redo work that looked complete. Someone else’s work can take longer to correct than fresh work takes to install.
These are site-visit-only jobs. Never give a firm phone price on a takeover job. You can read more about that in this guide to giving a price over the phone.
Walk the work. Check what is visible. Find out what is missing. Take dated photos before you touch anything. Those photos are your record of what you walked into.
Then write the scope around your work. State what you are responsible for and what you are not. Many contractors will not warranty another contractor’s work. Your contract should say which parts are yours.
Give urgent calls a different response
Some takeover calls cannot wait. There may be an open roof before rain. The house may have the water shut off. The customer may have no working kitchen or bathroom. There may be a move-in date.
Other jobs can wait a week.
Find out which one you are dealing with on the first call. You need that answer before you move your schedule.
If the job does not fit your trade, schedule, or type of work, say no cleanly and early. You can use this approach for turning down a job.
Write a new contract for your part of the job
Do not just “pick up” the old contract.
Write a new contract for your work. Identify the work you will perform. Identify the work you will not perform. State what existing work you are relying on, what you may need to repair or redo, and which parts you will not warranty.
If you sign the contract in the customer’s home, the federal 3-day cancellation rule may apply. See the 3-day cancellation rule for signed contracts.
Bella can capture the takeover story while you are working
Nail the Call’s receptionist is Bella, an AI receptionist for contractors. She answers every call, day or night.
During setup, you tell her your trades, service area, hours, price ranges, and what counts as an emergency. You can change her answers any time.
Bella works out the job: what the work is, how big it is, where it is, and when the caller wants it done. If the caller asks something technical, she writes it down for you instead of making it up. She will never quote a number you did not approve.
Urgent calls, such as water coming through a ceiling, get you a text right away. Every call ends with a text summary: name, number, address, job, budget, and what the caller said, in plain words.
On a takeover call, that means the story and the key facts are on your phone before you call back. Bella can also book the visit on your calendar.
Pricing is flat monthly. Starter is $95. Growth is $295. Pro is $495. There are no per-call limits, no per-minute meter, and no overage fees. See how it works.
Keep the first-call question list next to the phone. Look before you price. Put in writing exactly what is yours.
Keep reading
- Paying subs in 2026: the 1099-NEC line moved from $600 to $2,000The federal 1099-NEC line for paying subs went from $600 to $2,000 for 2026 payments. You will file fewer forms. You still need the W-9 before the first check.
- What a missed call actually costs your contracting businessWork out the real number for your own shop, using jobs you have already booked this year.
- The nine questions to ask on every remodel callGet budget, scope, and timeline out of a first call without making it feel like an interrogation.
- Voicemail, answering service, or receptionist: what actually fits a contracting shopAn honest comparison of the three ways to handle calls you cannot take, including where each one fails.
- The after-hours call policy every contracting shop needsDecide which calls are worth answering at night, who they go to, and what happens to the rest.
- How to spot a tire kicker on the phone, before you drive outThe signals that separate a serious customer from someone collecting numbers, and how to handle both.
- Should you charge for estimates? A straight answer for contractorsWhen charging wins you better work, when it costs you jobs, and how to introduce a fee properly.
- How many times to follow up with a lead before you let it goA follow-up schedule that keeps slow leads alive without turning you into the shop that will not stop calling.
- 3-day right to cancel for contractors: the FTC Cooling-Off RuleThe contractor's 3-day right to cancel: what to hand over at the kitchen table, when you can cash the deposit, and when the rule does not apply.
- While you're here: how to handle extra work requests without eating the costHow to price and write up the small add-ons customers ask for mid-job, so nobody is surprised at the final invoice.
- How to turn down a job without burning the leadHow to say no to the wrong job so the caller still remembers you well when the right job comes along.
- Why customers stand you up on estimate visits, and how to stop itMost no-shows are booking problems, not customer problems. Fix the booking call and the days before the visit.
- The EPA lead paint rule: what every trade needs to know about pre-1978 homesThe trigger is the age of the house and how much paint you disturb, not your trade. Ask what year it was built before you book.
- The unhappy customer call: how to handle a complaint after the job is doneMost complaint calls are about something small. Silence is what makes them expensive. Call back the same day, sort the problem, and book a real return date.
- Should you give a price over the phone? How to answer 'what will it cost?'Give a range when a few questions and photos can get you close, book a visit when the price hides behind a wall, and write down every number you say.
- The customer wants to buy their own materials: how to say yes without eating the riskCustomer-supplied materials can work, but only with rules set before the job: approve the product, check the boxes before the start day, warrant your labor only, and set a charge for lost days.
- When can you start? How to answer when you're booked weeks outThe hopeful date and the flat 'we're booked out' both lose jobs. Separate the visit date from the start date, tie the range to your real calendar, and tell a wrong-fit caller early.
- 'I'm getting three quotes': how to answer the caller who is shopping aroundGetting several quotes is normal homework, not an insult. Ask what was missing from the others, book the visit on the first call, and write a quote that is easy to compare line by line.
- 'Are you licensed and insured?': how to answer it on the phoneThe question often comes right before the caller hangs up. Answer it in one specific sentence, name the coverage you carry, and text proof before they put the phone down.
- Collecting the final payment: how to get paid in full when the job is doneThe final check rarely stalls because the customer cannot pay. It stalls over one small item nobody wrote down. Here is how to close out a job and leave with the money.
- How long should an estimate stay good? Setting an expiration date when material prices moveA quote with no end date promises your price and your calendar forever. One line on the estimate fixes that, and it keeps you from an awkward call weeks later.
- What your crew needs to know before the first morning: the handoff from the person who sold the jobThe person who sold the job heard the whole story. The crew lead got part of it. A one-page handoff before day one closes that gap.
- Rain day: what to tell the customer when weather pushes the job backThe customer is almost never upset that it rained. They are upset that they had to call to find out. Here is how to make the weather call first.
- Asking for reviews and referrals: when to ask, how to ask, and what not to doThe best time to ask for a review is the final walkthrough, in person, with a link in a text the same day. Here is the full habit, plus the review rules that trip shops up.
- Job photos: what to shoot before, during, and after every jobThe shop with a before photo of that crack can text it back and the call ends calmly. The shop without one argues from memory. Here is the photo habit that settles it.
- Markup vs margin: why a 20 percent markup is not a 20 percent profit"I put 20 percent on everything" sounds like a 20 percent profit. It is not. Here is the math from the margin you need to the markup you charge, and what a discount really costs.
- Order the materials before you promise the start dateThe start date you give a customer is only as good as your slowest material. Here is how to confirm lead times, order early, and catch a wrong delivery before it stops the crew.
- Working in a lived-in home: the house rules and daily cleanup that keep the customer on your sideMost mid-job calls are not about the work. They are about the dog that got out, the truck in front of the neighbor's mailbox, and the dust on the dining table. Here is how to stop those calls before they start.
- Allowances in an estimate: how to write them so they don't turn into a fightThe estimate said "tile allowance" and a number. Then the customer came back from the showroom. How to write allowances so the overage, the labor, and the deadline are settled before anyone signs.
- When your sub doesn't show up: how to protect the schedule and the customer's trustThe customer finds the empty house before you hear about it. How to confirm subs, build slack into the schedule, and tell the customer first when a trade misses a day.
- Your workmanship warranty: what to put in writing before the jobA spoken promise turns into an argument months later. How to write a short workmanship warranty: one length, one start date, a plain not-covered list, and an inspect-first rule.
- Raising your prices: how to tell past customers without losing themThe hard part of a price increase is the repeat customer who calls and says "same as last time." How to pick a start date, send a short heads-up, and hold the new price calmly.
See it in action
Book a short walkthrough and we’ll show you Bella taking a call for a shop like yours.
Book a walkthrough
15 minutes, no pitch deck.
Or just call us
(628) 895-9788